1. Define the task in a process brief
Describe the culture, desired product, operating mode and scale target before choosing a particular instrument. Distinguish working from total volume, microbial from cell-based cultivation, suspension from surface growth, and short experiments from prolonged cultures. System selection and reactor types explain these choices.
Deliverable: a concise process brief containing known requirements, open questions and the origin of each numerical input. A target volume range without a load profile does not describe a complete process system.
2. Obtain design information from suitable experiments
Process development connects an experimental question with the next equipment decision. Mixing and mass transfer and scale-up explain why gas flow, agitation speed and vessel volume alone do not establish transferability. Heat removal, local concentration gradients and culture behaviour can also limit performance.
Assign reference conditions to each design quantity: medium, temperature, fill level, gas composition, pressure and process phase, where relevant. Additional decimal places do not remove uncertainty. Carry missing information forward as assumptions that the project must test.
3. Establish scope and interfaces
| Area | Evidence to agree |
|---|---|
| Utilities | Pressure, temperature, quality and load at the user point |
| Cleaning and sterile boundary | A suitable concept for the complete product path |
| Sensors and software | Functions, data, alarms and recovery |
| Sampling and harvest | Sample identity and downstream transfer |
| Existing system | Reuse based on condition and evidence |
Specify the boundary between the supplier's scope and site responsibilities. A connected component may limit the combined function even when it falls outside the reactor quotation.
Further worked cases: Calculate equipment occupancy and waiting times
4. Preselect suppliers by task
The manufacturer directory provides profiles and a searchable comparison. The task matrix links to examples for laboratory systems, retrofit, stainless-steel production, single-use, adherent cultures and photobioreactors. Location, published reactor types and focus support preliminary selection; they do not confirm suitability for a particular project.
For each mandatory criterion, distinguish what is offered, what has been demonstrated and what requires a test. “Not mentioned” means unknown, not automatically unavailable. Written supplier responses should identify the model, configuration and agreed demonstration method.
5. Compare quotations on the same basis
Consider consumables, media, cleaning, operating effort, maintenance, spares and usable equipment time alongside purchase costs. Process economics explains system boundaries and sensitivities. Resource and environmental assessment needs a common functional unit, such as a defined amount of usable product, for a fair comparison.
A useful quotation comparison separates firm commitments, options, exclusions and unresolved points. A low base price may reflect an incomplete scope. A longer feature list may include functions that add little value to the intended process.
6. Plan acceptance and subsequent operation early
Write testable requirements rather than general quality adjectives. Requirements and evidence and function-based acceptance connect ordering with testing. A water run can demonstrate technical functions; it does not by itself demonstrate biological performance.
Documentation, training, backups, spare-part provision and responsible contacts belong in handover. Changes after acceptance require assessment of their consequences. The practitioner route connects later operation with troubleshooting and continuous learning.
Detailed learning paths and complete worked cases
Work through one question along its three connected chapters. Each path includes assumptions, reproducible cases and useful further sources. Use the chapter terminology lists to resolve unfamiliar prerequisites.
| Question | Chapter path | Outcome |
|---|---|---|
| Assess thermal exposure | Thermal exposure → Steam quality and condensate → Temperature mapping and evidence | Integrate temperature histories and identify the limits of sterilisation evidence. |
| Design experiments that support decisions | Factorial design analysis → Blocking & replication → Response surfaces & confirmation | Arrange factors, blocks and replication so effects remain distinguishable. |
| Close a perfusion balance | Cell retention → Perfusion balances → Perfusion productivity | Calculate medium exchange, cell retention and actual product harvest separately. |
| Assess viscous and filamentous cultures | Non-Newtonian broths → Filamentous morphology → Measuring mixing power | Relate flow curves, morphology and mechanical power to the same process question. |
| Describe spatial and temporal differences | Tracer and residence time → Compartment models → Cell lifelines | Interpret tracer data, compartment models and cell paths as different information. |
| Plan harvest and downstream together | Harvest campaigns → Membrane sizing → Chromatography cycles | Calculate membrane area, column cycles and occupation time within a process chain. |
| Coordinate capacity and utilities | Batches & occupancy → Utility load profiles → Capacity & bottlenecks | Expose queues, peak loads and bottlenecks through a schedule. |
| Account for light and photoproductivity | Light measurement → Light attenuation → Photobioreactor productivity | Specify the measured quantity, light path and area/volume basis before comparing. |
| Connect nitrogen conversion and aeration | Nitrogen balances → Alkalinity → Oxygen demand | Reconcile nitrogen, alkalinity and oxygen balances. |
| Assess supplier proposals transparently | Assessing supplier evidence → Comparing bioreactor configurations → Service, changes and the equipment lifecycle | Compare evidence, mandatory functions and lifecycle against the same task. |
Terms in this chapter
24 terms explained in the glossary
- Agitation speed
- Alkalinity
- Bioreactor
- Blocking
- Cell retention
- Chromatography
- Cleaning
- Condensate
- Downstream processing (DSP)
- Equipment maintenance
- Equipment occupancy time
- Exposure
- Functional unit
- Harvest
- Independent replication
- Load profile
- Perfusion
- Photobioreactor
- Product recovery
- Retrofitting
- Scale-up
- Steam quality
- Sterilisation
- Temperature mapping