Plan batches, material and resources together

A campaign is a planned sequence of production and supporting activities sharing resources. Its duration does not follow from cultivation time alone. Preparation, sample assessment, harvest, cleaning and restoration of usable equipment can extend occupancy. Some activities may also overlap when their dependencies and resources permit. Planning therefore represents material flow and equipment occupancy separately before connecting them.

First define the beginning and end of the system. Does the clock start at cell-bank thawing, production-reactor preparation or production inoculation? Does it stop at crude-product recovery, a completed pool or a separate quality decision? Each boundary may be useful but answers a different question. A supplier throughput or published productivity can only be transferred when its time boundary matches.

The teaching case starts at hour zero with preparation of the first production reactor. Its endpoint is completion of modelled downstream equipment occupancy. No later product-release time is invented. Two identical reactors feed one shared recovery train. All six batches and their durations are synthetic. The case makes waiting and bottlenecks visible; its hold limit is an exercise assumption rather than a measured product-stability value.

Use an activity table rather than one batch duration

Each batch occupies its reactor for twelve hours of preparation, 96 hours of culture, eight hours of harvest and transfer, and twelve hours of cleaning and restoration. Reactor occupancy is therefore 128 h. Material becomes available to downstream processing at hour 116 relative to batch start. Reactor availability and material handover are different events. Treating them as identical incorrectly shifts either the next reactor start or the possible downstream start.

The recovery train is represented here as one exclusive 80 h block per batch, including all states required before its next use. This is a separate campaign example with deliberately different durations from the detailed clarification, UF/DF and capture case. Values from those cases cannot be combined without recalculation. A practical schedule would expand the 80 h block into its actual activities and resources.

A useful activity table identifies batch, material identity, predecessor, exclusive resource, earliest start, duration and release event. Staffing is not calculated by treating every machine-running hour as active labour. Instead, actual interventions are recorded with skills and time windows. Equipment can run during a long culture while a particular manual sampling or changeover task still creates a shared staffing bottleneck.

Calculate the schedule with a simple event rule

For one downstream train, each batch starts at the later of material readiness and the end of the preceding occupancy. Write si = max(ri, ei−1) and ei = si + pi, where r is readiness, p is occupancy duration and e is completion. Waiting is wi = si − ri. Every quantity must use the same absolute time axis.

The rule separates two reasons for delay: material may be missing, or equipment may still be occupied. Additional conditions such as staffing availability can enter as further earliest-start constraints. A hard completion deadline is different; it is checked against the calculated outcome. If the schedule misses it, another sequence, additional demonstrated capacity or a justified process change is needed.

The dataset uses intervals including the start and excluding the end. Occupancy from 116 to 196 h blocks the resource immediately before 196 h; the next occupancy may begin at exactly 196 h. This prevents a shared boundary from being counted as an artificial overlap. Any necessary handover or switching time must already be included in the preceding block or represented separately. A mathematical convention must not erase practical transition time.

Six early starts create a growing queue

The first scenario starts a batch every 64 h, alternating between reactors R1 and R2. Each reactor therefore receives a new batch every 128 h and is fully occupied. Batch starts are 0, 64, 128, 192, 256 and 320 h. Corresponding material-readiness times are 116, 180, 244, 308, 372 and 436 h.

The first downstream operation starts at 116 h and ends at 196 h. Batch two is ready at 180 h but waits 16 h. Subsequent batches continue to arrive faster than the train can process them. Waiting times become 0, 16, 32, 48, 64 and 80 h, totalling 240 batch-hours. This is a sum across six materials, not an extra duration to add to final completion.

Downstream completion times are 196, 276, 356, 436, 516 and 596 h. The shared recovery train therefore limits material output despite fully occupied reactors. Four batches exceed the hypothetical maximum wait of 24 h. The exercise does not automatically declare the materials destroyed; it shows that the proposed schedule conflicts with the stated requirement. A defensible assessment of actual materials would need their real state and stability information.

The batch table lists every event, and the activity table records occupied resources. Both are generated by the same reproducible calculation. A changed release sequence and its consequences can therefore be checked without manually redrawing individual times.

Synthetic early release: readiness and queue
BatchReady (h)DSP start (h)Wait (h)DSP finish (h)
1116.0116.00.0196.0
2180.0196.016.0276.0
3244.0276.032.0356.0
4308.0356.048.0436.0
5372.0436.064.0516.0
6436.0516.080.0596.0

Match releases to actual outflow

The second scenario starts one batch every 80 h. Alternating reactors means that each reactor starts again after 160 h, leaving 32 h free between successive 128 h occupancies. Readiness times become 116, 196, 276, 356, 436 and 516 h. Each matches an available downstream start, eliminating all waiting in the deterministic model.

Final completion remains unchanged: the last batch again finishes at 596 h. Earlier and more intensive reactor use did not accelerate campaign completion; it merely placed material earlier in front of the limiting train. Matching release to outflow reduces intermediate inventory and hold exposure here without worsening the modelled endpoint. Free reactor time is consequently not evidence of poor overall performance.

This conclusion assumes that later starts are biologically and organisationally feasible. A prepared seed train cannot wait arbitrarily because a schedule contains a later number. The adjustment must propagate to relevant inoculum and medium preparation. Also check shift changes and utility demand: a better material sequence may move activities into less convenient windows. The deterministic calculation provides a testable scheduling option, not a universally optimal release policy.

Assign hold limits to the correct material state

The assumed 24 h limit begins when harvest handover is complete and ends at downstream start. It covers only the waiting interval between those events, not the entire harvest duration or automatically all subsequent processing. An actual stability statement must specify material state, vessel, temperature range, headspace and quality endpoint. A time without those conditions is not a transferable material acceptance criterion.

When harvest is collected over eight hours, its first portion is already older than its last at collection completion. A model with one readiness timestamp cannot resolve this age distribution. Time-sensitive products therefore need separate portions or a documented conservative age bound. This matters especially when processing starts before collection is complete. Mean collection time does not guarantee that the oldest portion remains within its permitted history.

Intermediate storage also requires physically available and suitable vessels. A calculated queue of two batches may require two separate containers and identities. One container twice as large is not equivalent when batches cannot be pooled. Sampling, state assessment and transfer must also match the vessel condition. The queue is therefore a real inventory requiring space, monitoring and handling, not merely a line on a timetable.

Identify hidden shared resources

A second process train may still share the buffer station, cleaning equipment, harvest pump, balance or qualified operator. List shared facilities alongside the main equipment. Assign each activity either an exclusive resource or a limited capacity requirement. For a shared balance, concurrent occupancy matters; for chilled water, the sum of time-dependent duty at the required temperatures is more relevant.

Some activities need several resources at once. A transfer may occupy source vessel, receiving vessel, pump, line and operator over the same interval. Reserving these resources independently can produce a superficially plausible but impossible combination. Check that all required states are available at each start. A delay must update dependent reservations; leaving a downstream start unchanged after its transfer has moved is a common planning error.

The time-dependent utility calculation supplements discrete equipment occupancy with additive loads. Both models use the same time axis but different conflict rules. Separate reactors may operate concurrently while their combined heating or gas demand exceeds supply. Conversely, a sufficiently large heat generator does not prove that an individual connection or exchanger can deliver local duty. The shared plan must preserve these distinctions.

Propagate a single delay through the sequence

In the paced 80 h scenario, extend only the third downstream operation by twelve hours. All other durations remain unchanged; no random distribution is invented. Batch three then finishes at 448 rather than 436 h. Batch four is ready at 436 h and waits twelve hours. Since material continues arriving every 80 h and subsequent occupancies also take 80 h, the backlog persists. Batches five and six each wait twelve hours as well.

Total waiting becomes 36 batch-hours and campaign completion moves to 608 h. Maximum waiting remains below the hypothetical 24 h limit. This does not establish a probability that a real campaign will meet the limit. The calculation examines one deterministic disruption. Frequency claims require suitable observations, justified distributions and dependencies between events.

The case shows that a perfectly matched average pace contains no built-in catch-up capacity. Responses could include an evidenced time allowance, occasionally shorter following work or an available additional resource. Another holding vessel can accommodate inventory but does not automatically increase processing capacity. A longer allowable age might resolve a conflict, but it requires real material evidence and must not be entered simply to rescue the schedule.

Include product changes and campaign boundaries explicitly

Repeating identical batches is simpler than changing products. A change may require different cleaning, parts, media, analytical methods and record checks. These demands can depend on sequence: A after B need not require the same time or evidence as B after A. One average changeover duration can conceal important differences. A multi-product plan therefore needs a defined transition matrix or individually evidenced change activities.

The first and last batch may also differ from the interior of a campaign. Buffers may not yet be prepared initially, while the final state may require extended storage preparation or dismantling. The calculated 596 h applies only to the six batches and states shown. Multiplying this duration by the number of planned campaigns accounts for boundary work only if it is already included within each boundary.

A useful handover record therefore goes beyond the last product pool. It states which equipment is available afterwards, which materials remain in inventory and which assessments lie outside the timing model. This final state must match the next planning round's starting state. A model that begins every campaign with ideally empty, prepared and available resources can repeatedly omit work between campaigns.

Compare planned and observed times consistently

During actual execution, record event timestamps and the reason for each deviation. A late start may reflect missing material, occupied equipment, an investigation or a deliberate rescheduling decision. These causes suggest different improvements. One unexplained lateness indicator can direct action towards the wrong activity. Classification should provide a testable process observation rather than retrospective blame.

Keep timestamps and time zones consistent. Different system clocks can create an apparently negative transfer time or overlapping occupancy. Establish actual event order before evaluating performance. Missing finish times must remain missing; replacing them with planned finishes cannot support a claim of observed schedule adherence.

Finally, compare identical start and finish events. If the plan includes complete cleaning but the observed duration stops at production completion, equipment appears artificially faster. Improvement analysis first aligns material and resource states, then calculates timing differences. The MIT introduction to flow and queues supplies the general relationship between inventory, throughput and time; defining the actual bioprocess boundary remains the task of the particular model.

Work backwards from the required finish

Backward calculation identifies latest starts compatible with a required finish. Six fully serial downstream occupancies of 80 h ending by 600 h need the first downstream start no later than 120 h. Since material becomes ready 116 h after reactor preparation begins, the first preparation could start no later than hour four in the ideal model. Starting at zero leaves four hours of schedule headroom under those assumptions.

This is not a general statistical allowance. It applies only while durations remain unchanged and no further resource limits operation. Adding twelve hours to the third downstream activity moves completion to 608 h, beyond the deadline. Working backwards with mean durations therefore does not prove reliable actual completion. It first identifies activities with little timing flexibility.

For parallel branches, a joining activity waits for the latest required predecessor. If material is ready at 116 h but required buffer only at 124 h, downstream processing cannot start before 124 h even with free equipment. Completion moves to 604 h. The eight-hour buffer delay is not added again to every batch if that one preparation serves all six. Exact resource allocation prevents both missing and repeatedly counted delays.

Expose recovery time through a slightly wider release interval

The matched 80 h pace contains no spare recovery time. In another sensitivity, widen releases to 84 h. Without disruption, material and downstream starts occur every 84 h, leaving four free hours between 80 h occupancies. The last of six batches finishes at 116 + 5 × 84 + 80 = 616 h. Extra reserve therefore extends undisturbed completion compared with 596 h.

If only the third downstream operation again takes twelve hours longer, its material is ready at 284 h and processing finishes at 376 h. Batch four is ready at 368 h, waits eight hours and finishes at 456 h. Batch five waits four hours and finishes at 536 h. Batch six can begin without waiting at its readiness time of 536 h and finishes at 616 h. Four spare hours per following interval progressively remove the backlog.

The example shows a specific trade-off: undisturbed production is slower, but the selected disruption no longer changes its final completion. It does not make 84 h a universally suitable pace. Another disruption time, longer delay or already constrained shared resource can change the result. Select headroom using relevant disturbances and real requirements rather than a generally preferred utilisation percentage.

Handover a scheduling change with a concise decision record

Handover a new release sequence with the specific objective it improves. In the 80 h case, that objective is to process six batches by 596 h while meeting the hypothetical waiting limit. The comparison changes release times only; processing durations and nominal quantities stay fixed. This description makes it possible to determine whether implementation actually matches the analysed option.

The record includes assumed starting states, supported durations, remaining assumptions and effects on dependent activities. A later production start must, for example, fit inoculum readiness. Changed night-time occupancy may create additional organisational conditions. Attach these points to the relevant activity rather than gathering vague caveats. Planners can then check which condition is already satisfied and which requires evidence.

After execution, compare predicted and observed events. A successful first run supports the particular observed option under its conditions; it does not demonstrate control of every disruption. The next iteration uses the new durations and causal observations. The schedule becomes a transparently maintained working model that remains understandable when another person takes over or an equipment component changes.

Questions for a defensible schedule

Exercise 1: Must batch three wait for its reactor with a 64 h start interval? No. It restarts in R1 at 128 h, exactly when R1's first occupancy finishes. The reactor schedule is feasible. Its material nevertheless waits 32 h for the shared downstream train. Conflicts must be checked against the correct resource.

Exercise 2: Does pacing save 240 hours of campaign duration? No. The 240 batch-hours are waiting summed across materials. Both undisrupted single-train scenarios finish at 596 h. The reduction concerns intermediate inventory and material age rather than the last completion time.

Exercise 3: Is an extra twelve hours spent on batch three automatically recovered later? No. With equal arrival intervals and subsequent occupancy durations, a twelve-hour backlog persists. Spare processing capacity or changed arrivals are needed to remove it.

Exercise 4: What information is needed before adding a second downstream train? In addition to its own capability, shared supporting resources must be able to serve both trains. Then recalculate the schedule. Without further constraints, the simplified six-batch campaign ends at 516 h with two trains. The different effects on throughput and completion time are examined separately in the next chapter.

Methods and data dictionary

MIT: Basic Concepts in Queueing explains general flow quantities and exposes the assumptions of particular waiting-time models. None of its distribution assumptions is imposed on biological batches here. Spirax Sarco: Steam Accumulators adds context on staggered demands and their limitations. The batch case itself is an independent deterministic calculation.

In campaign_schedule.csv, scenario identifies the option, batch the batch number and reactor the resource. Columns ending in _h contain hours as timestamps or durations. wait_h runs from harvest_ready_h to dsp_start_h. hold_limit_exceeded checks only the assumed 24 h limit. nominal_product_kg is an assumed quantity before a separate quality decision; when a requirement is violated it must not be reported as accepted product. The program and summary contain all scenarios.